Approvals of Goverment of India / Rajasthan under FCA 1980

 

2016

1.  Final sanction of diversion of forest land 0.16 hac in Construction of Eco     

     Enviornment Center in Sikar FA 27.1.2016 IP24.7.2013

2.  Final sanction of diversion of forest land 0.4273 hac in Construction of

    diversion chanal from forest nalah under flood protection scheme in Baran FA

     11.3.2016 IP 1.1.2016

3.   Final sanction of diversion of forest land 5.9882 hac in western dedicated

     fraight corridor in Alwar, Ajmer, Pali and Sikar FA 31.3.2016 IP 14.9.2015

4.  Final sanction of diversion of 224.517 forest land for Bikaner Phalodi NH 15

    Bikaner division 144.217 and jodhapur division 80.300

5.   Diversion of forest land of 0.10375 hac. for approach road for petrol pump  

     at Jayal in Nagore District

6. Diversion of 0.1441 Hac. forest land in favor of Essar Oil Limited  for construction of approach road in village Chak 7 BLMA  tehsil Vijaynagar District ganganagar

7. Diversion of 0.1502 hac. of forest land in favor of Essar Oil Limited for construction of approach road in Suratgarh - Sriganganagar road NH 15

2015

1.  Final sanction of diversion of land 4.4181 hac. for rehabilitation and upgradation two lane with paved shoulder for Padi Dahod NH 113

2.  Final sanction of diversion of land 0.745 hac widing and stregthen of existing highway Bheem Gulabpura NH 148 D

3.  Final sanction of diversion of 15.44 hac. for upgradation of Ghosunda Dam in Chittorgarh district.

4.Final sanction  of diversion of BArmer Sanchore section NH15 of 158.732 hac. 6.7.2015, 23.9.2015 and 16.11.2015

5. Final Sanction of Diversion of Phalodi - Jaisalmer NH15 KM 163.400 to 323.857 km in Jodhapur 74.118 hac. and JAisalmer 221.615 hac. Dated 23.7.2015, 21.10.2015 and 19.11.2015

6. Final Sanction of diversion of Jaisalmer-Barmer NH-15 km 5.00 to 153 km Jaisalmer 59.770 Ha. and Barmer 56.776 Ha. Dated 06.07.2015 and 23.09.2015 and 15.10.2015

7. Final sanction of diversion of 3.00 Hac. of forest land for construction of Bedach ka naka dam in Charbhuja Jilwara village water supply scheme district Rajsamand dated  21-07-2015 & 14-08-2015

8. Final sanction of diversion of 78.0131 ha. of forest land for widening of Kishangarh-Udaipur-Ahmedabad section of NH-79A, NH-79, NH-76 & NH-8 for existing 4 lane to 6 lane in the state of Rajasthan on dated 5.5.2015 & 9.6.2015

9.  Final sanction of diversion of forest land 12.2332 ha. in Karuli District and 12.0458 ha. in Dholpur District (24.2790 ha.) for Construction of 2 lane with paved shoulder of Karuli to Dholpur section of NH-11B (Km 83.500 to Km 186.750) in the state of Rajasthan on dated 15.6.2015 & 25.6.2015

10.  Final sanction of diversion of 0.30 ha. forest land for construction of Dhobhi Ghat & 0.015 ha. forest land for construction of Sulabh Complex at NLCP Pichola Udaipur dated 29.4.2015 & 9.6.2015

11.  Letter regarding updation of FCA proposals on egreenwatch

12.  Diversion of 16.2101 Ha. Forest Land for Mining of red Okar in favor of 5 lease holder near Manji ka Gudha District Chittorgarh

13. 220 KV D/C LILO for Amberi in Udaipur (N) (0.75 ha) dated 9.1.2015

14.  IOC A/R for petrol pump (Smt. Madhu Bhatia) at Chak 5 DBN, Vill.- Bhagwangarh,  teh.-Suratgarh on NH-15  km. 202.22 - 202.265 LHS in Ganganagar (0.096 ha), dated 12.2.2015

15.  Development, operation and maintenance of 132 kv transmission line for evacuation of 126 MW wind energy from 132/33 kv substation of Welspun to RRVPNL 132/33 KV Pratapgarh GSS. Welspun Renewables Energy Pvt. Ltd. in Pratapgarh (2.416 ha), dated - 27.3.2015

16.  PGCIL 765 KV T/L Gwalior to Jaipur in Karauli (72.42 ha), dated- 31.3.2015

17.  ONGC Exploratory drilling for prospecting oil / gas hydrocarbons  in Chambal Valley in  Devtra FB, Teh.-Ladpura, in Kota (1.53 ha) dated - 8.4.2015

 

 2014

1.  New BG Rail Line between Bangargram to Raas in Pali (5.5282 ha) - dated-6.2.2014

2.  400 KV SC TL from Alwar to Hindaun by Aravalli Transmission Service Co.Ltd. in Bharatpur (0.156+0.138 ha) - dated - 6.2.2014

3.  Hindustan Zinc Ltd., To increase the capacity of Gosundha Dam  in Chittorgarh (15.44 ha) dated 3.3.2014

4.   PGCIL 66 KV Earth electrode T/L at HVDC Bhiwadi SS in Alwar (12.075 ha) dated - 6.3.2014

5.  MORTH Widening of Beawar-Baghana section from km. 58.245 to 147 of NH- 8 in Ajmer (35.784 Ha) and Rajasmand (25.309 Ha) Total - 61.093 Ha, dated 2.5.2014

6.  PWD Widening of Ghati portion of 4 Km. Todabhim - Balaji road (MDR - 142) in Karauli (0.5375 ha) - dated 15.5.2014

7.  Education Deptt. Construction of Sr. Sec. School building at Malkeda in Sikar (0.8437 ha) - dated 19.5.2014

8.  DRDO establishment of strategic Defence project at Kho - Jajor in Alwar (850 Ha)- dated 26.5.2014

9.  PGCIL 400 KV DC Agra - Sikar TL (1.932 Ha, including re-diversion of 0.184 ha of PF of NH-8) in Jaipur dated 6.6.2014

10.  Prospecting & survey of mineral Iron ore by M/S Kalyani Mining Ventures Pvt. Ltd & Kalyani Natural Resources Pvt. Ltd in ML no. 48 & 49 / 2010 near vill. Todpura & Loloti, teh. Hindaun, construction of A/R & platform in Karauli (2.3425 Ha) - dated 12.06.2014

11.  Prospecting & survey of mineral Iron ore by M/S Kalyani Mining Ventures Pvt. Ltd & Kalyani Natural Resources Pvt. Ltdin ML no. 47 & 50 / 2010 near vill. Dedroli & Khora, teh. Hindaun, construction of A/R & platform in Karauli (4.764 Ha) - dated 12.06.2014

12.  PWD Widening of road from Ladi ka Bas to Sanwalpura Tanwran via Jeetala Jaitpura Km. 13/500 - 36/10 in Sikar (8.757 ha) dated - 18.7.2014

13.   DRDO establishment of strategic Defence project at Roopnagar in Pali (370 ha) dated - 23.7.2014

14. NHAI Missing link on Dausa Manoharpur road Km. 32/500 to 33/600 of NH-11-A (Jamuwa Ramgarh WLS) in Jaipur (4.17 ha) dated - 25.7.2014

15. Construction of new Arnaya Bhawan in Jaipur (0.64 ha) dated 28.7.2014

16. PWD Construction of 4 lane divided carriageway from NH-8 km 225 to Shagun Hotel via Ganesh Tekri with 2 no's Parking in Rajsmand (7.35 ha) dated - 28.7.2014

17. PWD Construction of road from MDR 114 km 11 to Dewlodi km 0/0 to 2/800 in Sikar (0.57 ha) dated - 6.8.2014 Final sanction of diversion of land 4.4181 hac. for rehabilitation and upgradation two lane with paved shoulder for Padi Dahod NH 113

18.  PWD Construction of missing link road from Chipalata - Ganeshwar km 6 to Hirwala km 0/0 to 0/900 in Sikar (0.60 ha) dated - 6.8.2014

19.  PWD Construction of road from Raipur-Patan-Jaitpura to Gadratta km 0/0 to 2/0 in Sikar (0.73 ha) dated - 6.8.2014

20.  Renewal of diversion of ML for marble in favour of Sh Ganesh Kr. Aggarwal, in Dariyarampura, tehsil-Srimadhopur in Sikar (27.3234 ha) - dated 7.8.2014

21.  BPCL Kota - Jaipur pipe line in Bundi (1.18 ha) RTR SWM (2.12 ha) & Tonk (0.72 ha) Total Area = 4.08 ha dated 8.9.2014

22.  Laying of MS pipe line from Bhaisrodgarh to Bunjar Khurd under Chambal - Bhilwara drinking water supply project in Bhilwara (1.350 ha), Kota MNP (2.570 ha) and Chittorgarh (0.878 ha), Total area - 4.798 ha, and re-diversion of 3.60 ha in Bhilwara district, dated 10.8.2014

23.  Ahmedi Irrigation Project in Baran (228.76 ha) dated - 14.10.2014

24.  Sathur Mataji minor Irrigation project in tehsil - Hindoli, Bundi (27.51 ha) dated - 30.10.2014

25.  BPCL A/R for petrol pump (Sh. Bhagwan Dan Charan) at Vill.- Jalipa, Jaisalmer - Barmer road RHS of NH-15 km. 142/497.26 to 142/537.50 , Barmer (0.036 ha) dated - 13.11.2014 

26.  IOC A/R for petrol pump (Sukhram Choudhary) on NH-65  km. 180.874 LHS, vill. Chugawas, Nagaur (0.0204 ha) dated - 13.11.2014

27.  IOC A/R for petrol pump (Rukhmani Devi) on NH-15  km. 248.646 LHS, vill. Berigaon, Teh. Gudamalani, Barmer (0.0651 ha) dated - 13.11.2014

28.  IOC A/R for petrol pump (Sh. Ajay Pareek) at Khasra No. 1383/1121, Vill./ tehsil - Shri Dungargarh, on Agra - Bikaner RHS of NH-11 Ch. 490 / 791 - 490 / 837, Bikaner (0.057118 ha) dated - 13.11.2014

29.  NHAI Upgradaion of Jodhpur - Pokaran section of NH-114 km. 11 to 175.433, Jodhpur (0.611 ha) dated - 13.11.2014

30.  PHED Drinking water tank & laying of pipe line in vill. - Mandoli, Nimera, Teh.- Dantaramgarh , Sikar (0.2212 ha) dated - 13.11.2014 

 

2013

1. RCC overhead service reservoir at Bhopan Ka Bara in Ajmer City (0.1075ha)- dated - 31.12.2013

2. Village-Ralawata (Jinmata) District- Sikar dated 08.11.2013 

3.  Krishanganj to Sanupur Road Construction dated 02.09.2013

4.  IOC Laying of crude oil pipe line for SMPL De-bottlenecking Project  in Jaipur (3.924 ha), Pali (1.648 ha) , Sirohi (0.805 ha) Total = 6.383 ha & Reuse of 14.1388 ha (Ajmer= 2.7758 +Pali = 1.608 + Sirohi=9.755 ) already diverted forest land Total Area = 20.5218 ha. dated - 8.8.2013

5.  400 KV DC Kalisindh TPS to 765 KV GSS Anta - Baran TL in Jhalawar (35.361 ha)- dated - 22.07.2013

6.  Diversion of forest land in Tikhiai Chotiyaan FB - in Udaipur (4.6467 ha) - dated 18.04.2013

7.  200 K.V.D./C Lilo Madri Vidhyut Line District- Udaipur dated 08.03.2013

Final sanction of diversion of land 4.4181 hac. for rehabilitation and upgradation two lane with paved shoulder for Padi Dahod NH 113